Lift cable bundle 1 with the left hand underneath the left end of the cable management
arm (black arrow). See Figure 3. Use the right hand to support the other end.
Set the left end of the cable bundle on to the left end of the cable support arm, next to
the blue handle (white arrow). See Figure 4. Let the cables
hang down as shown.
The following steps fasten the front and rear arms to the right rail (viewed from rear).
See Figure 5.
Figure 5. Cable management arm, front and rear fastened to rail
At the end of the rear arm (red arrow, Figure 5), locate the rear arm
tab and fasten it to the rail. See Figure 6.
Figure 6. Fastening rear arm to rail
At the front of the rack, slide the management enclosure rails out half way. See Figure 5.
Latch the cable management front arm (white arrow, Figure 5) to rail. It is above
the support arm pivot point.
From the front of the rack, pull the cable management front arm to the
front.