Before you begin
DANGER
HEAVY EQUIPMENT: PERSONAL INJURY OR EQUIPMENT DAMAGE MAY
RESULT IF MISHANDLED (D006)
Procedure
-
Verify that the customer has two ac power sources for each rack being installed.
-
Verify that the customer has ordered, supplied, and routed the following cables to the storage
facility being installed.
Note: Routing of the customer cables must not be billed against the installation. If the customer
wants the service representative to route the cables, that activity must be coded or billed
separately.
-
Fibre Channel cables from external systems to the storage facility host adapters.
-
An Ethernet LAN cable from the customer network to the primary customer network connection for
each management console.
Note: A second customer network connection to each management console can be added by RPQ.
-
Go to the next section.